Steel cutting ceremony for the 2nd vessel designed by Skipsteknisk

On 11th February 2025, we celebrated the steel cutting ceremony for “Bn83/REM Ocean” at Song Cam, Vietnam. This is an important milestone and an impressive achievement, just 2.5 months after entering the contract with Myklebust Verft.

It is great to mark this important milestone “Steel Cutting” for REM Offshore second vessel under construction at Song Cam. The first vessel, Bn82/REM Pioneer, is already sitting heavily on the slipway. We are really looking forward to the next important milestones: “Launching of the first hull Bn82 and keel laying of Bn83”. Both are scheduled for early summer 2025. “Stay Tuned,” says Kristian Stavset, Head of Projects at REM Offshore